SYDNEY, April 30 /Medianet International-AsiaNet/ –
Allegiance Mining ( ASX Code: AGM) is pleased to present its quarterly
results ending 30th March 2007. Following are the main points of what has been
achieved. A full copy is available on the Allegiance mining website.
AVEBURY NICKEL PROJECT IMPLEMENTATION
* Construction is at full pace and production is scheduled to commence in the
4th Quarter 2007.
* The main long-lead item, the primary ball mill has been fabricated by
Outokumpu Technology Australia and the largest mill component, the shell
barrel, was delivered to Avebury site on 20 April 2007 - 17 days ahead of
schedule.
* Engineering firm, Metplant of Perth relocated its construction team to the
Avebury process plant site in January-February and site construction offices
are fully equipped and staffed.
* The project will mill 900,000 tonnes of ore producing 8,500 tonnes of nickel
(“Ni”) in concentrates pa. The revised business plan currently extends to June
2016 - to extend as resources expand.
* All infrastructure components including roads, Tasmanian grid
hydro-electrical power, water management systems, site construction office and
Zeehan office–accommodation are complete.
* The Avebury nickel mine is fully operational and has delivered 10,000 tonnes
of normal run-of-mine ore to stockpile. Ore geometry and grades encountered to
date are as planned.
* The entire senior management team for the Avebury Project has been
successfully recruited.
EXPLORATION
* BISON discovery was announced during the Quarter. This is not yet included in
resources.
* The North Avebury Extended orebody has been extended a further 200 metres
below previous drilling – this too is not yet included in resources.
* In-fill drilling at East Avebury-Saxon is continuing and an initial resource
has been announced.
* Resources increased 15% to 12 million tonnes grading 1.11% Ni containing
131,000 tonnes of Ni at a 0.7% Ni cut-off grade. Application of strict new
resource classification boundaries, Ore Reserves stand at 3.35 million tonnes
grading 1.16% Ni, sufficient for initial production to mid 2011.
* Infill drilling will commence in the mine in mid-May so as to materially
increase reserves by year-end, well ahead of production to allow an early
assessment of mill-mine expansion options.
* Orebody widths are typically 10 metres to 40 metres in good ground conditions.
* Drilling west and especially east of the known resource is encountering
additional mineralisation.
FINANCE & CORPORATE
* Cash balance at the end of March stood at $39.15 million.
* Share placement to Jinchuan Nickel Group of China raised A$4 million,
announced in January.
MARKETING
US$2.8 billion offtake agreement with Jinchuan Nickel Group of China remains a
cornerstone agreement that brings major benefits to the Avebury Nickel Project.
TASK 2007
Q1 Q2 Q3 Q4
Infrastructure
(roads, power, water, office & accommodation) Completed
Ventilation & Service Shafts,
Pump Station & Mine Power Completed
Mine Contract and Mobilisation Completed
Mill Site, Water Management &
Tailings Storage Facility Completed
Mill Design & Engineering 60% completed
Mill Procurement 90% completed
Mill & Process Plant Construction 20% completed
Mill & Process Plant Commissioning
Nickel Production
Chairman, Tony Howland-Rose said “Mining operations commenced in earnest
during the Quarter with 10,000 tonnes of ore now stockpiled. All sectors of the
mine and mine site are now connected to the State hydroelectric grid.
Construction and fabrication continue apace, with major equipment items
arriving on site – including the ball mill shell which arrived early! The
mechanical completion date remains in place with October-November being the
target.
During the Quarter, Allegiance shares became a component of the Standard &
Poors ASX 300 index, and as such, gained qualification for investment by a
broad range of local and overseas institutions. This, in part, may account for
the recent firm share price.
I have many conversations with shareholders each quarter and the soaring
nickel price is top of the list. I believe that the nickel price will remain
firm for the next few years. Only when the increase in production of new mined
nickel exceeds the increase in demand will nickel prices fall. New uses may
well add materially to this demand. Many of you will be aware that Toyota has
announced that in the future, it expects all of its cars to be hybrids. If
Toyota delivers this plan, it will require 500,000 additional tonnes of nickel
for those hybrid electric batteries. Current annual world production of
nickel will not exceed 1,400,000 tonnes.
Thus good times for nickel and great times ahead for Allegiance!
SOURCE: Allegiance Mining NL
A full copy of this announcement is available on the Allegiance website.
http://www.allegiance-mining.com.au/default.asp?id=21
Contact: Tony Howland-Rose, Chairman:
+612 9397 7777 or
+61 418 972 112
April 30, 2007
Sorry, comments are closed.